Contact Centre

The project required the removal of asbestos soffits to the external permitter of the building under fully controlled conditions. The contact center needed to remain live whilst the removal works were carried out.

pgrcvypgrcvypgrccropped
Project
Contact Centre
Value
Circa £60K
Duration
5 weeks
Sector
Council
Services
Licensable Asbestos Removal

The Challenge

All site staff required advanced DBS clearance. Works was required to be completed externally whilst not affecting the occuoants or visitors to the centre. Although additional asbestos material was identified the programme was worked through with the centre management to complete the removal with minimal disruption to the centre.

Our Delivery

  • Undertaking removal works without affecting the sites day to day operations.

  • Working on a daily basis with the sites manager to communicate the days activities.

  • Specialist subcontractors used (asbestos licensed scaffolders, UKAS analysts and surveyors)

  • External audit carried out to ensure highest possible standards were met.

ufd410ufd410ufd4cropped

Key Outcomes

  • Safety Result

    No noted incidents over the project.

  • Programme Result

    Programme achieved even through additional material located during removal.

  • Client Result

    Praise given on the planning and delivery.

Capabilities Used

01

UKAS Asbestos Surveying

02

Licensed asbestos removal

03

Waste management / compliance

04

Reinstatement